| No. |
Amount of Payment |
Milestone events for Indicative Scheduled Date |
Indicative Scheduled Date |
| 1. |
Ten (10) percent of price |
Deposit paid as follows (a) OMR 25,000 paid on sale of property at the signing of the Agreement (b) Balance of the 10% paid within seven (7) days after date of agreement
|
(a) Date of agreement
(b) Agreement date plus seven (7)seven days |
| 2. |
Fifteen (15) percent of price |
Completion of property foundations |
Construction start date (CSD) (to be advised by developer plus two (2) months) |
| 3. |
Fifteen (15) percent of price |
Completion of ground floor slab |
CSD plus three (3) months |
| 4. |
Fifteen (15) percent of pricel |
Completion of roof slab |
CSD plus six (6) months |
| 5. |
Fifteen (15) percent of price |
Completion of 1st fix mechanical |
CSD plus eight (8) months |
| 6. |
Fifteen (15) percent of price |
Completion of 2nd fix mechanical and electrical |
CSD plus ten (10) months |
| 7. |
Fifteen (15) percent of price |
Completion |
CSD plus twelve (12) months |